Short cut Technique For Time And Work :: Railway and SSC CHSL And All Competitive exams

  Time and work chapter is most important topic for railway and ssc all kind of competitive exams.

  Here we are providing the some short cut techniques from this chapter.

  Under this chapter, we will study the following:

        A.    How to calculate the required number of persons to complete a particular work in a stipulated time period?

        B.    How to calculate the required time to complete a particular work by certain number of persons?

  To find ‘A’ and ‘B’, the 1st and foremost task is to keep following basic point mind:
1.     While solving problems, the work done is always supposed to be equal to 1.
2.     If a person can do a piece of work in ‘n’ days, then that person’s 1 day work = 1/n.
3.     If a person 1 day’s work = 1/n, then the person will complete the work in ‘n’ days.
4.     A person works equally every day.

  Important Relations:

1.     Work and persons directly proportional (more work, more men and conversely more men, more work).
2.     Time and person inversely proportional (more men, less time and conversely more time, less men).
3.     Work and time directly proportional (more work, more time and conversely more time, more work).


   Some important techniques about Time and Work:

    TECHNIQUE 1:
                     If ‘M1’ persons can do ‘W1’ work in ‘D1’ days working T1 h in a day and ‘M2’ persons can do ‘W2’ work in ‘D2’ days working T2 h in a day, then we have a very basic and all in one relationship as

                                    M1D1T1W2 = M2D2T2W1

Example: 16 men can do a piece of a work in 10 days. How many men are needed to complete the work in 20 days?

Solution:  Here, M1=16, D1= 10, W1 = W2 = 1, D2 = 20, M2 =?
                  According to the formula, M1D1W2 = M2D2W1
                                                                 16X10X1 = M2X20X1
                                                                 M2 = 16X10/20 = 160/20
                                                                 M2 = 8 men
  
Alternate method:
                       To do a work in 10 days, 16 men are needed.
                       To do the work in 1 day, 16X10 men are needed.
                       Here, to do the work in 20 days, = 1610/20 = 160/20
                                                                                  = 8 men are needed.

TECHNIQUE 2:
     
If A can do a piece of work in ‘x’ days and B can do the same work in ‘y’ days then

                            (A+B)’s 1 day’s work = 1/x+1/y

     Inverse of (A+B)’s 1 day’s work = time taken by (A+B) to complete the work
  
  Note: this formula is also applicable for 3 or more persons

Example: A  can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days, then working together, how many days will they take to complete the work?

Answer: A’s 1 day’s work = 1/4
                B’s 1 day’s work=1/8
                C’s 1 day’s work=1/12
              Therefore (A+B+C)’s 1 day’s work =1/4+1/8+1/12= 6+3+2/24
                                                                           = 11/24
              Therefore (A+B+C) complete the whole work in 24/11 days

TECHNIQUE 3:

If A and B can do a piece of work in X days, B and C can do the same work in y days and A and C can do it in z days, then working together, A, B, and C can do that work in

                                               2xyz/ xy+ yz+zx days.

Example: A and B can do a piece of work in 3 days. B and C can do the same work in 9 days while C and A can do it in 12 days. Find the time in which A, B, and C can finish the work, working together.

Answer:  According to the formula
            = 2x3x9x12/3x9+9x12+3x12
            = 2x3x9x12/27+108+36
            = 2x3x9x12/171
            = 6x12/19
            = 72/19 days.

TECHNIQUE 4:
       If ‘x’ takes ‘a’ days more to complete a work than the time taken by (x+ y) to do same work and ‘y’ takes ‘b’ days more than the time taken by (x+y) to do the same work, then (x+y) do the work in

                                           Square root of a b days  

Example: when A alone does a piece of work, he takes 16 days more then the time taken by (A+B) to complete that work while B alone takes 9 days more than the time taken by (A+B) to finish the work. What time, A and B together will take to finish this work?

Answer: according to the formula, where A= 16 B= 9
                 Required answer: square root of 16x9 = 4x3 = 12 days.
                  Answer = 12 days.

Technique 5:
A and B, each alone can do a piece of work in ‘a’ and ‘b’ days, respectively. Both begin together and if
  i. A leaves the work ‘X’ days before its completion, then total time taken for completion of work will be given as

                          T = (a+x) b/ (a+b)

ii. B leaves the work ‘x’ days before its completion, then total time taken for completion of work will be given as

                          T = (b+x)a/(a+b)

Example: A can do a piece of work in 10 days while B can do it in 15 days. They begin together but 5 days before completion of the  work, B leaves off. Find the total number ofdays for the work to be completed.

Answer: here, a=10 days, b= 15 days, x= 5, t=?
 According to the formula,
             Required time T = (b+x)a/(a+b)
                                        = (15+5)10/10+15
                                        = 4X2 = 8 days

Technique 6:

A and B do a piece of work in ‘a’ and ‘b’ days, respectively. Both begin together but after some days, A leaves off and the remaining work is completed by B in ‘x’ days. Then, the time after which A left, is given by                                             
                                      T= (b-x) a / a+b.
Example: A and B do a piece of work in 40 days and 50 days, respectively. Both begin together but after certain time, A leaves off. In this case B finishes the remaining work in 20 days.After how many days did a leave?

Answer: given that a= 40 days, b=50 days, X=20, t =?
                  Required time = (b-x) a/ a+b
                                          = (50-20) 40 / 50+40
                                          = 30X40 / 90
                                           = 40 / 3   days
  
  



Short cut Technique For Time And Work :: Railway and SSC CHSL And All Competitive exams Short cut Technique For Time And Work :: Railway and SSC CHSL And All Competitive exams Reviewed by Mani Babu on 16:40:00 Rating: 5
Powered by Blogger.